Projects
44 surtax-funded projects
South Ocala Elementary - New Classroom Wing
Over Budget$39.7M
$34.5M spent
Hammett Bowen Jr Elementary - Gymnasium Addition
$21.1M
$14.7M spent
Shady Hill Elementary - Gymnasium Addition
$18.2M
$6.2M spent
Howard Middle School - Building 3 AC Replacement
Delayed Over Budget$12.9M
$2.5M spent
Fort King Middle School - Chiller Plant Upgrade
$10.9M
$4.2M spent
West Port High School - Media Center Expansion
Over Budget$10.8M
$2.1M spent
Liberty Middle School - HVAC Replacement Phase 4
Delayed$9.3M
$9.1M spent
Liberty Middle School - Administration Building Remodel
$7.8M
$3.9M spent
Hammett Bowen Jr Elementary - Drainage Improvements
Delayed Over Budget$6.1M
$2.3M spent
Evergreen Elementary - Security Camera System
Delayed$5.4M
$3.6M spent
Sparr Elementary - Roof Restoration
$5.2M
$3.6M spent
Dunnellon High School - Building 1 AC Replacement
$5.1M
$3.7M spent
South Ocala Elementary - Roof Replacement Building 4
$5.1M
$2.2M spent
Forest High School - Accessible Restroom Conversion
Delayed Over Budget$5.0M
$2.5M spent
Osceola Middle School - Drop-off Loop Redesign
Over Budget$5.0M
$3.7M spent
Madison Street Academy - Roof Restoration
$4.6M
$3.5M spent
Ward-Highlands Elementary - Security Camera System
$4.5M
$3.0M spent
North Marion Middle School - ADA Accessibility Upgrade
Delayed$4.3M
$1.6M spent
Osceola Middle School - Fencing & Access Control
$4.2M
$1.7M spent
Dunnellon Middle School - Emergency Communication System
$4.1M
$3.3M spent
Madison Street Academy - Administration Building Remodel
$4.1M
$1.3M spent
Harbor View Elementary - Fencing & Access Control
$3.9M
$1.5M spent
Greenway Elementary - HVAC Replacement Phase 3
$3.9M
$1.3M spent
Sparr Elementary - Emergency Communication System
$3.8M
$1.5M spent
Madison Street Academy - Parking Lot Expansion
Over Budget$3.5M
$1.7M spent
North Marion High School - Athletic Field Renovation
Over Budget$3.5M
$2.0M spent
Romeo Elementary - Parking Lot Expansion
$3.5M
$1.4M spent
West Port High School - Roof Restoration
Delayed$3.0M
$868K spent
North Marion High School - Building Renovation Phase 2
$2.9M
$915K spent
Oakcrest Elementary - Smart Classroom Technology
$2.9M
$1.3M spent
Evergreen Elementary - Chiller Plant Upgrade
$2.9M
$1.2M spent
Howard Middle School - Fencing & Access Control
Delayed$2.7M
$2.4M spent
South Ocala Elementary - Building Renovation Phase 5
Delayed Over Budget$2.6M
$1.1M spent
Oakcrest Elementary - Athletic Field Renovation
Delayed$2.4M
$869K spent
Howard Middle School - Science Lab Renovation
$2.4M
$1.9M spent
Stanton-Weirsdale Elementary - Accessible Restroom Conversion
$2.2M
$830K spent
Marion Oaks Elementary - Full Roof Replacement
$2.2M
$697K spent
North Marion Middle School - Drainage Improvements
$1.8M
$484K spent
Maplewood Elementary - ADA Accessibility Upgrade
$1.6M
$646K spent
Emerald Shores Elementary - Building 4 AC Replacement
$1.5M
$729K spent
Dunnellon Elementary - ADA Accessibility Upgrade
$1.5M
$593K spent
Dunnellon Middle School - Network Infrastructure Upgrade
Over Budget$1.2M
$738K spent
Dunnellon Elementary - Emergency Communication System
$1.1M
$560K spent
North Marion Middle School - Drop-off Loop Redesign
$1.1M
$369K spent