Dunnellon High School - Building 1 AC Replacement

Project Detail

Dunnellon High School - Building 1 AC Replacement

Low Risk
Hvac Active SC-2025-042 Dunnellon High School
68%

Overall

Complete

Original Budget

$5.1M

Current Budget

$5.1M

Spent to Date

$3.7M

Remaining

$1.5M

Vendor

TopCoat Roofing LLC

Health Score

82.0/100

Data Source: This project uses demonstration data for display purposes.

Project Details

Description
HVAC project at Dunnellon High School
Category
Hvac
Expenditure Type
Capital
Contract ID
SC-2025-042
School
Dunnellon High School

Schedule

Start Date
Feb 19, 2025
Original End Date
Jul 14, 2026
Current End Date
Jul 14, 2026

Timeline Progress

2025-02-19 2026-07-14

Budget Breakdown

Original Amount
$5,123,000
Current Amount
$5,123,000
Total Paid
$3,660,200
Remaining
$1,462,800

Spending Progress

Budget Utilization 71.4%
Work Completion 68.7%

Spending is slightly ahead of work progress

No phase data available for this project

No inspection records available

Contractor Information

Vendor Name
TopCoat Roofing LLC
Contract ID
SC-2025-042
Contract Type
N/A

No community engagement records

No committee actions for this project

No documents uploaded for this project

Documents will appear here when added