Emerald Shores Elementary - Building 4 AC Replacement

Project Detail

Emerald Shores Elementary - Building 4 AC Replacement

Low Risk
Hvac Active SC-2025-007 Emerald Shores Elementary
53%

Overall

Complete

Original Budget

$1.5M

Current Budget

$1.5M

Spent to Date

$729K

Remaining

$784K

Vendor

TechConnect Solutions

Health Score

85.0/100

Data Source: This project uses demonstration data for display purposes.

Project Details

Description
HVAC project at Emerald Shores Elementary
Category
Hvac
Expenditure Type
Capital
Contract ID
SC-2025-007
School
Emerald Shores Elementary

Schedule

Start Date
Jan 24, 2025
Original End Date
Jan 14, 2027
Current End Date
Jan 14, 2027

Timeline Progress

2025-01-24 2027-01-14

Budget Breakdown

Original Amount
$1,513,000
Current Amount
$1,513,000
Total Paid
$729,000
Remaining
$784,000

Spending Progress

Budget Utilization 48.2%
Work Completion 53.4%

Spending is tracking with or below work progress

No phase data available for this project

No inspection records available

Contractor Information

Vendor Name
TechConnect Solutions
Contract ID
SC-2025-007
Contract Type
N/A

No community engagement records

No committee actions for this project

No documents uploaded for this project

Documents will appear here when added