Howard Middle School - Fencing & Access Control

Project Detail

Howard Middle School - Fencing & Access Control

Schedule Delay Medium Risk
Safety & Security Active SC-2025-039 Howard Middle School
89%

Overall

Complete

Original Budget

$2.7M

Current Budget

$2.7M

Spent to Date

$2.4M

Remaining

$304K

Vendor

AccessAbility Builders

Health Score

50.0/100

Data Source: This project uses demonstration data for display purposes.

Project Details

Description
Safety & Security project at Howard Middle School
Category
Safety & Security
Expenditure Type
Capital
Contract ID
SC-2025-039
School
Howard Middle School

Schedule

Start Date
Jun 30, 2025
Original End Date
Mar 27, 2026
Current End Date
Mar 27, 2026
Delay
64 days — Subcontractor availability

Timeline Progress

2025-06-30 2026-03-27

Budget Breakdown

Original Amount
$2,713,000
Current Amount
$2,713,000
Total Paid
$2,409,000
Remaining
$304,000

Spending Progress

Budget Utilization 88.8%
Work Completion 89.7%

Spending is tracking with or below work progress

No phase data available for this project

No inspection records available

Contractor Information

Vendor Name
AccessAbility Builders
Contract ID
SC-2025-039
Contract Type
N/A

No community engagement records

No committee actions for this project

No documents uploaded for this project

Documents will appear here when added