Howard Middle School - Building 3 AC Replacement

Project Detail

Howard Middle School - Building 3 AC Replacement

Schedule Delay Over Budget High Risk
Hvac Active SC-2025-014 Howard Middle School
24%

Overall

Complete

Original Budget

$10.3M

Current Budget

$12.9M

Spent to Date

$2.5M

Remaining

$10.4M

Vendor

Central FL Renovations

Health Score

47.0/100

Data Source: This project uses demonstration data for display purposes.

Project Details

Description
HVAC project at Howard Middle School
Category
Hvac
Expenditure Type
Capital
Contract ID
SC-2025-014
School
Howard Middle School

Schedule

Start Date
Apr 29, 2025
Original End Date
Oct 16, 2027
Current End Date
Oct 16, 2027
Delay
110 days — Permitting issues

Timeline Progress

2025-04-29 2027-10-16

Budget Breakdown

Original Amount
$10,310,000
Current Amount
$12,865,000
Total Paid
$2,466,300
Remaining
$10,398,700
Budget Variance
+24.8%

Spending Progress

Budget Utilization 19.2%
Work Completion 24.7%

Spending is tracking with or below work progress

No phase data available for this project

No inspection records available

Contractor Information

Vendor Name
Central FL Renovations
Contract ID
SC-2025-014
Contract Type
N/A

No community engagement records

No committee actions for this project

No documents uploaded for this project