West Port High School - Media Center Expansion

Project Detail

West Port High School - Media Center Expansion

Over Budget Medium Risk
New Construction Active SC-2025-030 West Port High School
23%

Overall

Complete

Original Budget

$10.2M

Current Budget

$10.8M

Spent to Date

$2.1M

Remaining

$8.7M

Vendor

Stellar Construction Group

Health Score

65.0/100

Data Source: This project uses demonstration data for display purposes.

Project Details

Description
New Construction project at West Port High School
Category
New Construction
Expenditure Type
Capital
Contract ID
SC-2025-030
School
West Port High School

Schedule

Start Date
May 30, 2025
Original End Date
Sep 17, 2027
Current End Date
Sep 17, 2027

Timeline Progress

2025-05-30 2027-09-17

Budget Breakdown

Original Amount
$10,213,000
Current Amount
$10,841,000
Total Paid
$2,100,000
Remaining
$8,741,000
Budget Variance
+6.1%

Spending Progress

Budget Utilization 19.4%
Work Completion 23.1%

Spending is tracking with or below work progress

No phase data available for this project

No inspection records available

Contractor Information

Vendor Name
Stellar Construction Group
Contract ID
SC-2025-030
Contract Type
N/A

No community engagement records

No committee actions for this project

No documents uploaded for this project

Documents will appear here when added