Concerns

Issues requiring committee attention

Concerns to Review

Issues that may warrant committee attention or questions

Delayed Projects

10

Behind schedule

Over Budget

10

Exceeding budget

Total Concerns

16

10 delays, 10 cost issues

Schedule Delays

76 days late High Risk

Hammett Bowen Jr Elementary - Drainage Improvements

Weather delays

School: Hammett Bowen Jr Elementary

Budget: $6.1M | Spent: $2.3M

View Project
66 days late High Risk

Forest High School - Accessible Restroom Conversion

Weather delays

School: Forest High School

Budget: $5.0M | Spent: $2.5M

View Project
117 days late High Risk

South Ocala Elementary - Building Renovation Phase 5

Weather delays

School: South Ocala Elementary

Budget: $2.6M | Spent: $1.1M

View Project
110 days late High Risk

Howard Middle School - Building 3 AC Replacement

Permitting issues

School: Howard Middle School

Budget: $12.9M | Spent: $2.5M

View Project
64 days late Medium Risk

Howard Middle School - Fencing & Access Control

Subcontractor availability

School: Howard Middle School

Budget: $2.7M | Spent: $2.4M

View Project
92 days late Medium Risk

Liberty Middle School - HVAC Replacement Phase 4

Weather delays

School: Liberty Middle School

Budget: $9.3M | Spent: $9.1M

View Project
63 days late Medium Risk

West Port High School - Roof Restoration

Permitting issues

School: West Port High School

Budget: $3.0M | Spent: $868K

View Project
48 days late Medium Risk

Evergreen Elementary - Security Camera System

Change order processing

School: Evergreen Elementary

Budget: $5.4M | Spent: $3.6M

View Project
80 days late Medium Risk

Oakcrest Elementary - Athletic Field Renovation

Design modification required

School: Oakcrest Elementary

Budget: $2.4M | Spent: $869K

View Project
39 days late Medium Risk

North Marion Middle School - ADA Accessibility Upgrade

Supply chain delays

School: North Marion Middle School

Budget: $4.3M | Spent: $1.6M

View Project

Cost Overruns

+15.1% over budget High Risk

Hammett Bowen Jr Elementary - Drainage Improvements

School: Hammett Bowen Jr Elementary

Budget: $6.1M | Spent: $2.3M

View Project
+14.8% over budget High Risk

Forest High School - Accessible Restroom Conversion

School: Forest High School

Budget: $5.0M | Spent: $2.5M

View Project
+12.4% over budget High Risk

South Ocala Elementary - Building Renovation Phase 5

School: South Ocala Elementary

Budget: $2.6M | Spent: $1.1M

View Project
+24.8% over budget High Risk

Howard Middle School - Building 3 AC Replacement

School: Howard Middle School

Budget: $12.9M | Spent: $2.5M

View Project
+15.0% over budget Medium Risk

South Ocala Elementary - New Classroom Wing

School: South Ocala Elementary

Budget: $39.7M | Spent: $34.5M

View Project
+15.6% over budget Medium Risk

Osceola Middle School - Drop-off Loop Redesign

School: Osceola Middle School

Budget: $5.0M | Spent: $3.7M

View Project
+5.9% over budget Medium Risk

Madison Street Academy - Parking Lot Expansion

School: Madison Street Academy

Budget: $3.5M | Spent: $1.7M

View Project
+8.8% over budget Medium Risk

North Marion High School - Athletic Field Renovation

School: North Marion High School

Budget: $3.5M | Spent: $2.0M

View Project
+6.1% over budget Medium Risk

West Port High School - Media Center Expansion

School: West Port High School

Budget: $10.8M | Spent: $2.1M

View Project
+23.3% over budget Medium Risk

Dunnellon Middle School - Network Infrastructure Upgrade

School: Dunnellon Middle School

Budget: $1.2M | Spent: $738K

View Project