North Marion High School - Athletic Field Renovation

Project Detail

North Marion High School - Athletic Field Renovation

Over Budget Medium Risk
Site Improvements Active SC-2025-017 North Marion High School
70%

Overall

Complete

Original Budget

$3.2M

Current Budget

$3.5M

Spent to Date

$2.0M

Remaining

$1.5M

Vendor

Central FL Renovations

Health Score

62.0/100

Data Source: This project uses demonstration data for display purposes.

Project Details

Description
Site Improvements project at North Marion High School
Category
Site Improvements
Expenditure Type
Capital
Contract ID
SC-2025-017
School
North Marion High School

Schedule

Start Date
Feb 09, 2025
Original End Date
Feb 04, 2026
Current End Date
Feb 04, 2026

Timeline Progress

2025-02-09 2026-02-04

Budget Breakdown

Original Amount
$3,215,000
Current Amount
$3,498,000
Total Paid
$2,027,300
Remaining
$1,470,700
Budget Variance
+8.8%

Spending Progress

Budget Utilization 58.0%
Work Completion 70.6%

Spending is tracking with or below work progress

No phase data available for this project

No inspection records available

Contractor Information

Vendor Name
Central FL Renovations
Contract ID
SC-2025-017
Contract Type
N/A

No community engagement records

No committee actions for this project

No documents uploaded for this project

Documents will appear here when added