Dunnellon Elementary - ADA Accessibility Upgrade
Low Risk i !== 'SC-2025-033'); }
else { if (!ids.includes('SC-2025-033')) ids.push('SC-2025-033'); }
localStorage.setItem('surtaxWatchlist', JSON.stringify(ids));
watched = !watched;
" class="px-3 py-2 rounded-lg text-sm font-medium transition-all border"
:class="watched ? 'bg-blue-500/20 border-blue-500/40 text-blue-300' : 'bg-slate-800 border-slate-600 text-slate-400 hover:text-white hover:border-slate-500'">
44%
Overall
Complete
Original Budget
$1.5M
Current Budget
$1.5M
Spent to Date
$593K
Remaining
$896K
Vendor
SiteWorks Engineering
Health Score
86.0/100
Data Source: This project uses demonstration data for display purposes.
Project Details
- Description
- ADA Compliance project at Dunnellon Elementary
- Category
- Ada Compliance
- Expenditure Type
- Capital
- Contract ID
- SC-2025-033
- School
- Dunnellon Elementary
Schedule
- Start Date
- Jan 01, 2025
- Original End Date
- Nov 22, 2026
- Current End Date
- Nov 22, 2026
Timeline Progress
2025-01-01
2026-11-22