Liberty Middle School - HVAC Replacement Phase 4

Project Detail

Liberty Middle School - HVAC Replacement Phase 4

Schedule Delay Medium Risk
Hvac Active SC-2025-024 Liberty Middle School
94%

Overall

Complete

Original Budget

$9.3M

Current Budget

$9.3M

Spent to Date

$9.1M

Remaining

$214K

Vendor

SafeSchool Systems Inc

Health Score

55.0/100

Data Source: This project uses demonstration data for display purposes.

Project Details

Description
HVAC project at Liberty Middle School
Category
Hvac
Expenditure Type
Capital
Contract ID
SC-2025-024
School
Liberty Middle School

Schedule

Start Date
Feb 01, 2025
Original End Date
Mar 28, 2026
Current End Date
Mar 28, 2026
Delay
92 days — Weather delays

Timeline Progress

2025-02-01 2026-03-28

Budget Breakdown

Original Amount
$9,331,000
Current Amount
$9,331,000
Total Paid
$9,116,600
Remaining
$214,400

Spending Progress

Budget Utilization 97.7%
Work Completion 94.4%

Spending is slightly ahead of work progress

No phase data available for this project

No inspection records available

Contractor Information

Vendor Name
SafeSchool Systems Inc
Contract ID
SC-2025-024
Contract Type
N/A

No community engagement records

No committee actions for this project

No documents uploaded for this project

Documents will appear here when added