North Marion Middle School - Drop-off Loop Redesign

Project Detail

North Marion Middle School - Drop-off Loop Redesign

Low Risk
Site Improvements Active SC-2025-013 North Marion Middle School
32%

Overall

Complete

Original Budget

$1.1M

Current Budget

$1.1M

Spent to Date

$369K

Remaining

$691K

Vendor

Central FL Renovations

Health Score

90.0/100

Data Source: This project uses demonstration data for display purposes.

Project Details

Description
Site Improvements project at North Marion Middle School
Category
Site Improvements
Expenditure Type
Capital
Contract ID
SC-2025-013
School
North Marion Middle School

Schedule

Start Date
Jun 20, 2025
Original End Date
Aug 09, 2027
Current End Date
Aug 09, 2027

Timeline Progress

2025-06-20 2027-08-09

Budget Breakdown

Original Amount
$1,060,000
Current Amount
$1,060,000
Total Paid
$368,900
Remaining
$691,100

Spending Progress

Budget Utilization 34.8%
Work Completion 32.1%

Spending is slightly ahead of work progress

No phase data available for this project

No inspection records available

Contractor Information

Vendor Name
Central FL Renovations
Contract ID
SC-2025-013
Contract Type
N/A

No community engagement records

No committee actions for this project

No documents uploaded for this project

Documents will appear here when added