Oakcrest Elementary - Athletic Field Renovation
Schedule Delay Medium Risk i !== 'SC-2025-026'); }
else { if (!ids.includes('SC-2025-026')) ids.push('SC-2025-026'); }
localStorage.setItem('surtaxWatchlist', JSON.stringify(ids));
watched = !watched;
" class="px-3 py-2 rounded-lg text-sm font-medium transition-all border"
:class="watched ? 'bg-blue-500/20 border-blue-500/40 text-blue-300' : 'bg-slate-800 border-slate-600 text-slate-400 hover:text-white hover:border-slate-500'">
37%
Overall
Complete
Original Budget
$2.4M
Current Budget
$2.4M
Spent to Date
$869K
Remaining
$1.6M
Vendor
AccessAbility Builders
Health Score
63.0/100
Data Source: This project uses demonstration data for display purposes.
Project Details
- Description
- Site Improvements project at Oakcrest Elementary
- Category
- Site Improvements
- Expenditure Type
- Capital
- Contract ID
- SC-2025-026
- School
- Oakcrest Elementary
Schedule
- Start Date
- Jun 01, 2025
- Original End Date
- Dec 23, 2026
- Current End Date
- Dec 23, 2026
- Delay
- 80 days — Design modification required
Timeline Progress
2025-06-01
2026-12-23