Liberty Middle School - Administration Building Remodel

Project Detail

Liberty Middle School - Administration Building Remodel

Low Risk
Renovation Active SC-2025-022 Liberty Middle School
51%

Overall

Complete

Original Budget

$7.8M

Current Budget

$7.8M

Spent to Date

$3.9M

Remaining

$4.0M

Vendor

SiteWorks Engineering

Health Score

81.0/100

Data Source: This project uses demonstration data for display purposes.

Project Details

Description
Renovation project at Liberty Middle School
Category
Renovation
Expenditure Type
Capital
Contract ID
SC-2025-022
School
Liberty Middle School

Schedule

Start Date
May 12, 2025
Original End Date
Jan 02, 2027
Current End Date
Jan 02, 2027

Timeline Progress

2025-05-12 2027-01-02

Budget Breakdown

Original Amount
$7,848,000
Current Amount
$7,848,000
Total Paid
$3,888,200
Remaining
$3,959,800

Spending Progress

Budget Utilization 49.5%
Work Completion 51.8%

Spending is tracking with or below work progress

No phase data available for this project

No inspection records available

Contractor Information

Vendor Name
SiteWorks Engineering
Contract ID
SC-2025-022
Contract Type
N/A

No community engagement records

No committee actions for this project

No documents uploaded for this project

Documents will appear here when added