Hammett Bowen Jr Elementary - Gymnasium Addition

Project Detail

Hammett Bowen Jr Elementary - Gymnasium Addition

Low Risk
New Construction Active SC-2025-037 Hammett Bowen Jr Elementary
70%

Overall

Complete

Original Budget

$21.1M

Current Budget

$21.1M

Spent to Date

$14.7M

Remaining

$6.4M

Vendor

SafeSchool Systems Inc

Health Score

87.0/100

Data Source: This project uses demonstration data for display purposes.

Project Details

Description
New Construction project at Hammett Bowen Jr Elementary
Category
New Construction
Expenditure Type
Capital
Contract ID
SC-2025-037
School
Hammett Bowen Jr Elementary

Schedule

Start Date
Jan 08, 2025
Original End Date
Nov 04, 2025
Current End Date
Nov 04, 2025

Timeline Progress

2025-01-08 2025-11-04

Budget Breakdown

Original Amount
$21,065,000
Current Amount
$21,065,000
Total Paid
$14,690,900
Remaining
$6,374,100

Spending Progress

Budget Utilization 69.7%
Work Completion 70.5%

Spending is tracking with or below work progress

No phase data available for this project

No inspection records available

Contractor Information

Vendor Name
SafeSchool Systems Inc
Contract ID
SC-2025-037
Contract Type
N/A

No community engagement records

No committee actions for this project

No documents uploaded for this project

Documents will appear here when added