School Lookup

Find surtax-funded projects by school

School Lookup

26 schools with surtax-funded projects

South Ocala Elementary

Elementary School

3 projects
Total Budget $47.4M
Avg Completion
62.0%
1 delayed project

Hammett Bowen Jr Elementary

Elementary School

2 projects
Total Budget $27.2M
Avg Completion
56.0%
1 delayed project

Shady Hill Elementary

Elementary School

1 project
Total Budget $18.2M
Avg Completion
39.0%

Howard Middle School

Middle School

3 projects
Total Budget $18.0M
Avg Completion
63.0%
2 delayed projects

Liberty Middle School

Middle School

2 projects
Total Budget $17.2M
Avg Completion
73.0%
1 delayed project

West Port High School

High School

2 projects
Total Budget $13.8M
Avg Completion
29.0%
1 delayed project

Madison Street Academy

School

3 projects
Total Budget $12.2M
Avg Completion
56.0%

Fort King Middle School

Middle School

1 project
Total Budget $10.9M
Avg Completion
41.0%

Osceola Middle School

Middle School

2 projects
Total Budget $9.3M
Avg Completion
67.0%

Sparr Elementary

Elementary School

2 projects
Total Budget $9.0M
Avg Completion
50.0%

Evergreen Elementary

Elementary School

2 projects
Total Budget $8.3M
Avg Completion
49.0%
1 delayed project

North Marion Middle School

Middle School

3 projects
Total Budget $7.2M
Avg Completion
34.0%
1 delayed project

North Marion High School

High School

2 projects
Total Budget $6.4M
Avg Completion
53.0%

Dunnellon Middle School

Middle School

2 projects
Total Budget $5.4M
Avg Completion
72.0%

Oakcrest Elementary

Elementary School

2 projects
Total Budget $5.4M
Avg Completion
45.0%
1 delayed project

Dunnellon High School

High School

1 project
Total Budget $5.1M
Avg Completion
69.0%

Forest High School

High School

1 project
Total Budget $5.0M
Avg Completion
59.0%
1 delayed project

Ward-Highlands Elementary

Elementary School

1 project
Total Budget $4.5M
Avg Completion
71.0%

Harbor View Elementary

Elementary School

1 project
Total Budget $3.9M
Avg Completion
42.0%

Greenway Elementary

Elementary School

1 project
Total Budget $3.9M
Avg Completion
31.0%

Romeo Elementary

Elementary School

1 project
Total Budget $3.5M
Avg Completion
36.0%

Dunnellon Elementary

Elementary School

2 projects
Total Budget $2.6M
Avg Completion
49.0%

Stanton-Weirsdale Elementary

Elementary School

1 project
Total Budget $2.2M
Avg Completion
33.0%

Marion Oaks Elementary

Elementary School

1 project
Total Budget $2.2M
Avg Completion
33.0%

Maplewood Elementary

Elementary School

1 project
Total Budget $1.6M
Avg Completion
40.0%

Emerald Shores Elementary

Elementary School

1 project
Total Budget $1.5M
Avg Completion
53.0%