Sparr Elementary - Roof Restoration

Project Detail

Sparr Elementary - Roof Restoration

Low Risk
Roofing Active SC-2025-011 Sparr Elementary
62%

Overall

Complete

Original Budget

$5.2M

Current Budget

$5.2M

Spent to Date

$3.6M

Remaining

$1.7M

Vendor

AccessAbility Builders

Health Score

85.0/100

Data Source: This project uses demonstration data for display purposes.

Project Details

Description
Roofing project at Sparr Elementary
Category
Roofing
Expenditure Type
Capital
Contract ID
SC-2025-011
School
Sparr Elementary

Schedule

Start Date
Jan 09, 2025
Original End Date
Jul 03, 2026
Current End Date
Jul 03, 2026

Timeline Progress

2025-01-09 2026-07-03

Budget Breakdown

Original Amount
$5,243,000
Current Amount
$5,243,000
Total Paid
$3,577,500
Remaining
$1,665,500

Spending Progress

Budget Utilization 68.2%
Work Completion 62.0%

Spending is slightly ahead of work progress

No phase data available for this project

No inspection records available

Contractor Information

Vendor Name
AccessAbility Builders
Contract ID
SC-2025-011
Contract Type
N/A

No community engagement records

No committee actions for this project

No documents uploaded for this project

Documents will appear here when added