West Port High School - Roof Restoration

School capital outlay surtax projects

Home / Contracts / West Port High School - Roof Restoration

West Port High School - Roof Restoration

Surtax
SC-2025-044 · AccessAbility Builders · West Port High School Active Delayed 63d
57

Health

Medium Risk

Original Amount

$2,967,000

Current Amount

$2,967,000

Total Paid

$868,200

Remaining

$2,098,800

Overall Progress

33%

Contract Details

Contract ID SC-2025-044
Surtax Category Roofing
Vendor AccessAbility Builders
School West Port High School

Description

Roofing project at West Port High School

Schedule

Start Date Feb 12, 2025
Original End Date Jun 02, 2027
Current End Date Jun 02, 2027

63 days behind schedule

Permitting issues

Budget Breakdown

Spent $868,200

29.3% of budget spent