Howard Middle School - Fencing & Access Control

School capital outlay surtax projects

Home / Contracts / Howard Middle School - Fencing & Access ...

Howard Middle School - Fencing & Access Control

Surtax
SC-2025-039 · AccessAbility Builders · Howard Middle School Active Delayed 64d
50

Health

Medium Risk

Original Amount

$2,713,000

Current Amount

$2,713,000

Total Paid

$2,409,000

Remaining

$304,000

Overall Progress

89%

Contract Details

Contract ID SC-2025-039
Surtax Category Safety & Security
Vendor AccessAbility Builders
School Howard Middle School

Description

Safety & Security project at Howard Middle School

Schedule

Start Date Jun 30, 2025
Original End Date Mar 27, 2026
Current End Date Mar 27, 2026

64 days behind schedule

Subcontractor availability

Budget Breakdown

Spent $2,409,000

88.8% of budget spent