West Port High School - Media Center Expansion
Surtax
SC-2025-030
· Stellar Construction Group
· West Port High School
Active
+6.1% Over Budget
65
Health
Medium Risk
Original Amount
$10,213,000
Current Amount
$10,841,000
Total Paid
$2,100,000
Remaining
$8,741,000
Overall Progress
23%Contract Details
Contract ID
SC-2025-030
Surtax Category
New Construction
Vendor
Stellar Construction Group
School
West Port High School
Description
New Construction project at West Port High School
Schedule
Start Date
May 30, 2025
Original End Date
Sep 17, 2027
Current End Date
Sep 17, 2027