Hammett Bowen Jr Elementary - Drainage Improvements

School capital outlay surtax projects

Home / Contracts / Hammett Bowen Jr Elementary - Drainage I...

Hammett Bowen Jr Elementary - Drainage Improvements

Surtax
SC-2025-028 · Stellar Construction Group · Hammett Bowen Jr Elementary Active Delayed 76d +15.1% Over Budget
31

Health

High Risk

Original Amount

$5,309,000

Current Amount

$6,110,000

Total Paid

$2,283,300

Remaining

$3,826,700

Overall Progress

41%

Contract Details

Contract ID SC-2025-028
Surtax Category Site Improvements
Vendor Stellar Construction Group
School Hammett Bowen Jr Elementary

Description

Site Improvements project at Hammett Bowen Jr Elementary

Schedule

Start Date Feb 25, 2025
Original End Date Jun 15, 2027
Current End Date Jun 15, 2027

76 days behind schedule

Weather delays

Budget Breakdown

Spent $2,283,300

37.4% of budget spent

Budget changed from $5,309,000 to $6,110,000 (+15.1%)