Hammett Bowen Jr Elementary - Drainage Improvements
Surtax
SC-2025-028
· Stellar Construction Group
· Hammett Bowen Jr Elementary
Active
Delayed 76d
+15.1% Over Budget
31
Health
High Risk
Original Amount
$5,309,000
Current Amount
$6,110,000
Total Paid
$2,283,300
Remaining
$3,826,700
Overall Progress
41%Contract Details
Contract ID
SC-2025-028
Surtax Category
Site Improvements
Vendor
Stellar Construction Group
School
Hammett Bowen Jr Elementary
Description
Site Improvements project at Hammett Bowen Jr Elementary
Schedule
Start Date
Feb 25, 2025
Original End Date
Jun 15, 2027
Current End Date
Jun 15, 2027
76 days behind schedule
Weather delays