Liberty Middle School - HVAC Replacement Phase 4
Surtax
SC-2025-024
· SafeSchool Systems Inc
· Liberty Middle School
Active
Delayed 92d
55
Health
Medium Risk
Original Amount
$9,331,000
Current Amount
$9,331,000
Total Paid
$9,116,600
Remaining
$214,400
Overall Progress
94%Contract Details
Contract ID
SC-2025-024
Surtax Category
HVAC
Vendor
SafeSchool Systems Inc
School
Liberty Middle School
Description
HVAC project at Liberty Middle School
Schedule
Start Date
Feb 01, 2025
Original End Date
Mar 28, 2026
Current End Date
Mar 28, 2026
92 days behind schedule
Weather delays