Liberty Middle School - HVAC Replacement Phase 4

School capital outlay surtax projects

Home / Contracts / Liberty Middle School - HVAC Replacement...

Liberty Middle School - HVAC Replacement Phase 4

Surtax
SC-2025-024 · SafeSchool Systems Inc · Liberty Middle School Active Delayed 92d
55

Health

Medium Risk

Original Amount

$9,331,000

Current Amount

$9,331,000

Total Paid

$9,116,600

Remaining

$214,400

Overall Progress

94%

Contract Details

Contract ID SC-2025-024
Surtax Category HVAC
Vendor SafeSchool Systems Inc
School Liberty Middle School

Description

HVAC project at Liberty Middle School

Schedule

Start Date Feb 01, 2025
Original End Date Mar 28, 2026
Current End Date Mar 28, 2026

92 days behind schedule

Weather delays

Budget Breakdown

Spent $9,116,600

97.7% of budget spent