Stanton-Weirsdale Elementary - Accessible Restroom Conversion

School capital outlay surtax projects

Home / Contracts / Stanton-Weirsdale Elementary - Accessibl...

Stanton-Weirsdale Elementary - Accessible Restroom Conversion

Surtax
SC-2025-021 · Sunshine State Contractors · Stanton-Weirsdale Elementary Active
84

Health

Low Risk

Original Amount

$2,210,000

Current Amount

$2,210,000

Total Paid

$829,500

Remaining

$1,380,500

Overall Progress

33%

Contract Details

Contract ID SC-2025-021
Surtax Category ADA Compliance
Vendor Sunshine State Contractors
School Stanton-Weirsdale Elementary

Description

ADA Compliance project at Stanton-Weirsdale Elementary

Schedule

Start Date Feb 23, 2025
Original End Date Jul 13, 2027
Current End Date Jul 13, 2027

Budget Breakdown

Spent $829,500

37.5% of budget spent