Howard Middle School - Building 3 AC Replacement
Surtax
SC-2025-014
· Central FL Renovations
· Howard Middle School
Active
Delayed 110d
+24.8% Over Budget
47
Health
High Risk
Original Amount
$10,310,000
Current Amount
$12,865,000
Total Paid
$2,466,300
Remaining
$10,398,700
Overall Progress
24%Contract Details
Contract ID
SC-2025-014
Surtax Category
HVAC
Vendor
Central FL Renovations
School
Howard Middle School
Description
HVAC project at Howard Middle School
Schedule
Start Date
Apr 29, 2025
Original End Date
Oct 16, 2027
Current End Date
Oct 16, 2027
110 days behind schedule
Permitting issues