South Ocala Elementary - New Classroom Wing

School capital outlay surtax projects

Home / Contracts / South Ocala Elementary - New Classroom W...

South Ocala Elementary - New Classroom Wing

Surtax
SC-2025-012 · AccessAbility Builders · South Ocala Elementary Active +15.0% Over Budget
61

Health

Medium Risk

Original Amount

$34,516,000

Current Amount

$39,685,000

Total Paid

$34,516,000

Remaining

$5,169,000

Overall Progress

99%

Contract Details

Contract ID SC-2025-012
Surtax Category New Construction
Vendor AccessAbility Builders
School South Ocala Elementary

Description

New Construction project at South Ocala Elementary

Schedule

Start Date Feb 25, 2025
Original End Date Mar 22, 2026
Current End Date Mar 22, 2026

Budget Breakdown

Spent $34,516,000

87.0% of budget spent

Budget changed from $34,516,000 to $39,685,000 (+15.0%)