Osceola Middle School - Fencing & Access Control

Surtax
SC-2025-010 · AccessAbility Builders · Osceola Middle School Active
82

Health

Low Risk

Original Amount

$4,243,000

Current Amount

$4,243,000

Total Paid

$1,723,500

Remaining

$2,519,500

Overall Progress

37%

Contract Details

Contract ID SC-2025-010
Surtax Category Safety & Security
Vendor AccessAbility Builders
School Osceola Middle School

Description

Safety & Security project at Osceola Middle School

Schedule

Start Date Apr 21, 2025
Original End Date Sep 08, 2027
Current End Date Sep 08, 2027

Budget Breakdown

Spent $1,723,500

40.6% of budget spent