Dunnellon Middle School - Network Infrastructure Upgrade

Surtax
SC-2025-008 · TechConnect Solutions · Dunnellon Middle School Active +23.3% Over Budget
68

Health

Medium Risk

Original Amount

$1,012,000

Current Amount

$1,248,000

Total Paid

$737,800

Remaining

$510,200

Overall Progress

69%

Contract Details

Contract ID SC-2025-008
Surtax Category Technology
Vendor TechConnect Solutions
School Dunnellon Middle School

Description

Technology project at Dunnellon Middle School

Schedule

Start Date Mar 24, 2025
Original End Date May 18, 2026
Current End Date May 18, 2026

Budget Breakdown

Spent $737,800

59.1% of budget spent

Budget changed from $1,012,000 to $1,248,000 (+23.3%)